xAI 在面临环境诉讼时安装 500 MW 燃气轮机
xAI 秘密向其密西西比州 Colossus 2 数据中心增建了 19 台总计 500 MW 的燃气轮机,引发 NAACP 诉讼,指控其违反《清洁空气法》。
Public records reveal xAI installed 19 portable gas turbines at its Colossus 2 site in Mississippi since March, adding over 500 MW of capacity. The NAACP and environmental groups filed a lawsuit alleging these turbines violate the Clean Air Act because they operate without permanent permits, a claim xAI disputes by citing temporary status exemptions. Eight of these new turbines were installed after the lawsuit was filed in April, bringing the total on-site count to 46 units. Regulators allowed xAI to claim a one-year permit exemption due to the turbines' portable nature, but environmental lawyers argue the massive scale effectively creates an unpermitted power plant. The NAACP has filed an emergency injunction to shut down the operations, citing environmental justice concerns similar to those raised at xAI's Tennessee Colossus 1 site.